Project identity
Project name
Schulneubau Heinrich-Hertz-Gymnasium am Ostbahnhof
As of: not applicable
Freshness: not applicable
Evidence
Evidence label: Verified — The displayed wording is faithfully supported by the cited source. It does not mean the value is current, the only official value, or that a conflicting value is resolved.
Schulneubau Heinrich-Hertz-Gymnasium am Ostbahnhof
Source publication date: not stated
Original source
Project location
Lange Straße/Straße der Pariser Kommune, 10243 Berlin – Friedrichshain-Kreuzberg
As of: not applicable
Freshness: not applicable
Evidence
Evidence label: Verified — The displayed wording is faithfully supported by the cited source. It does not mean the value is current, the only official value, or that a conflicting value is resolved.
Lange Straße/Straße der Pariser Kommune, 10243 Berlin – Friedrichshain-Kreuzberg
Source publication date: not stated
Original source
Current source-stated position
Project status
Die Umsetzung des Schulneubaus liegt im Zeitplan.
As of: 2026-06-19
Freshness: unassessed
Evidence
Evidence label: Verified — The displayed wording is faithfully supported by the cited source. It does not mean the value is current, the only official value, or that a conflicting value is resolved.
Die Umsetzung des Schulneubaus liegt im Zeitplan.
Source publication date: 2026-06-19
Original source
Milestone
Die technische Übergabe des Neubaus an den Bezirk ist für den 31.08.2026 geplant.
Milestone type: handover
Milestone term: technische Übergabe
Date: 31.08.2026 (exact day)
Qualifier: geplant
As of: 2026-06-19
Freshness: unassessed
The source planned this milestone for 31.08.2026 as of 2026-06-19. That date has passed, but no confirming source is recorded. Completion is not asserted.
Evidence
Evidence label: Verified — The displayed wording is faithfully supported by the cited source. It does not mean the value is current, the only official value, or that a conflicting value is resolved.
Die technische Übergabe des Neubaus an den Bezirk ist für den 31.08.2026 geplant.
Source publication date: 2026-06-19
Original source
Withheld facts
Organization role
This organization role is withheld because its role vocabulary remains unresolved.
Language boundary
Translation unverified. German source wording is canonical. English is used for structural labels only; unresolved types are withheld rather than guessed.